Norway

NORWAY

INEOS TA2022, Porsgrunn

Year: 2022
Number of workers: 116 persons
Scope of work: various repair works during shutdown

MS Fridtjof Nansen, Ulsteinvik

Year: 2019
Number of workers: 2 - 14 persons
Scope of work: Various interior works.

MS Roald Amundsen, Ulsteinvik

Year: 2019
Number of workers: 1 - 5 persons
Scope of work: Various interior works.

RS2019 Inovyn VCM and Chlorine plants, Porsgrunn

Year: 2019
Number of workers: 16 persons
Scope of work: Various repair works on old pipelines. Carbon and stainless steel, alloy. Diameters from 3/4 up to 400, thicknes up to 9,53mm. Welding method TIG, MMA and MIG/MAG.

MS Lofoten, RISSA

Year: 2019
Number of workers: 8 persons
Scope of work: Various repair works.

MS Richard With, RISSA

Year: 2018
Number of workers: 4 persons
Scope of work: Various repair works.

Shutdown, Yara, Glomfjord

Year: 2018
Number of workers: 11 persons
Scope of work: Various repair works on old pipelines and tanks. Installation and welding works on new pipelines. Stainless steel, DN100 - DN500. Thickness up to 6mm.

Super Pure project, Yara, Porsgrunn

Year: 2018
Number of workers: 10 persons
Scope of work: Installation and welding works of various pipelines and equipment. Stainless steel and Duplex, up to DN250. Thickness 3-6mm.

NORETYL - Projekt Ethylene Phase II

Year: 2016
Number of workers: 10 persons
Scope of work: Installation and welding works of various pipelines and equipment.